The following will hopefully document the construction of our long awaited new home at Lake Wilderness Country Club in Maple Valley, Washington. We hope you will enjoy watching the progress as much as we are.
PROGRESS The facings for the two Fisher&Paykel diswasher drawers have been installed. We now have our red front entry door. One hundred and ninety spindles have been installed on the stairway and railings for the loft.
LIGHT FIXTURES AND RANGE HOOD Several light fixtures have been added. All of the towel bars, etc. have been installed. The range hood and backplash have been installed.
"SOME" PROGRESS The wonderfufl fireplace facing tile has been removed. Apparently the gypsum wallboard had to be replaced with cement board per fireplace installation instructions. I guess we will soon see a new look to the fireplace facing. The two boxes of tiles await installation.
The landscapers have started the sprinkler system intallation.
STILL WORKING Work is still progressing even though we had snow. The closet guys have started work, the cabinet work continues and light fixtures have been delivered awaiting electricians.